What a weekly build-out report should tell a tenant off site
Separate finished work, decisions coming due and events that will change the next week’s plan.

This article is sponsored by Harrison Construction. Partner content policy
A tenant who visits a commercial job site only occasionally needs more from a weekly report than a few photographs. Ask the contractor to connect each image or update to a room and to the work it shows. A picture labeled with its date and location is much easier to use when discussing progress with someone who has never walked the site.
Flag the choices the tenant can still make
Keep owner decisions in their own section. For example, a fixture selection might need approval before a supplier can confirm shipment. List what is due, who can approve it and which scheduled work depends on it. If an item affects the budget or scope, agree on how to document the change through your usual project process.
Let next week’s work set the agenda
Ask the contractor to describe upcoming inspections, deliveries and spaces that will be unavailable. Put a date beside anything that needs coordination with the landlord or a vendor. On the next weekly call, begin with the open decisions from the previous report.
Harrison Construction describes regular owner reporting in its tenant finish-out service. Before a Dallas–Fort Worth build-out starts, ask the project team to share an example report and explain who you can contact when a decision cannot wait until the weekly call.
Visit Harrison Construction.